Thursday 6 May 2010

The latest updates will now be posted on the Bold Vision website - please go to:

ourboldvision.blogspot.com/p/bold-build.html
6 May
Last night the underflloor heating pipework was laid - John Hamilton, working with 4 volunteers, fixed the plastic pipes to the concrete reinforcement bars. Tomorrow morning the concrete will be laid, so we'll be ready to start the decorations on the weekend.
Hoping for volunteers Saturday and Sunday 11am.

Sunday 2 May 2010

1 May



Last night the builders finished spreading the hardcore fill, and today the damp-proof membrane was laid, followed by the thermal insulation. The second photo shows the steel reinforcement for the concrete slab being prepared